PROJECT HIGHLIGHTS

Size 43 LN FT; 1 Floor
Project Manager Olsen Construction
General Contractor Johnson & Goglia Contracting
Architect Haworth / Integrated Interiors
Product System Haworth Enclose Frameless Walls
Application Walls with Trim Finish and Hardware
Installation Timeline 2 days

Integrated Interiors (II) furnished and installed the Haworth Enclose Frameless Wall System within a dining facility in Westwood, MA.

Originally scheduled over five days, the project was completed in just two, due to early delivery of materials, skillful installation, and precise coordination between site supervisor and contractor.