PROJECT HIGHLIGHTS

Size 30,000 SQ FT; 1 Building / 2 Floors
Architect M&W
Project Management Leggat McCall Properties
Construction Turner Construction
Product System Haworth TecCrete 1250 bare, TecCrete HPL, Haworth Teknika Terrazzo; Practica Tile;  Julie Static Smart Carpet Tile
Application 18” finish floor height used to provide under floor air distribution (U.F.A.D.)
Installation Timeline  1 month

A key aspect of the project included installing multiple finishes  in different areas to provide impact and versatility to the functional areas.  The raised floor platform allowed for highly flexible and energy efficient office, training, lobby and kitchen environments.

Despite scheduling and coordination challenges, II succeeded in completing a timely installation.

Integrated Interiors (II) installed the first large-scale Haworth Teknica project at Massachusetts Green High Performance Computing Center (MGHPCC).  MGHPCC is the first multi-university research data center in the country.