Autodesk, Inc. / Waltham, MA

PROJECT HIGHLIGHTS

Size 11,250 SQ FT; 1 floor
Project Manager Integrated Interiors
General Contractor Consigli Construction
Product System Haworth TecCrete1250 Flooring
Application Raised Access Flooring
Installation Timeline 6 weeks

Integrated Interiors (II) completed a raised access flooring installation for the new headquarters for Autodesk, Inc., located in the Innovation and Design Building in the South Boston Seaport District. In a building undergoing complete rehabilitation, II successfully managed the installation process during regular business hours, working alongside multiple contractors and intersecting projects.

Using raised access flooring provided a stable base layer for an extremely out of level floor, while also enabling underfloor routing for electrical power and data cabling.